adsm08 3,678 #26 Posted November 12 7 hours ago, Handy Don said: Depending on how your town’s engineering department operated, and keeps records, they may well have a site plan on file from the original construction that shows the locations. In our village, anything built from the late 40’s onwards is on file. Yeah, they probably do, but doing anything involving the township is a pain because I'm pretty sure it's just one guy with a roll of duct tape and a pack of chewing gum. 1 Share this post Link to post Share on other sites
adsm08 3,678 #27 Posted Saturday at 11:08 PM No construction crews this week. Cement got moved back to Wednesday, garage door is being installed Monday. I got started on the electrical by myself today. Took good pictures of the sub-panel's insides, then disconnected everything, took it off the wall, and moved it out by the new door and reconnected the incoming power, and got one circuit partially hooked up. I started hooking up for the lights, so that I can actually get things done after work, got as far as getting the switch wired to the panel, and quit for the night because the next step is 14 ft in the air and I'd rather do that in the light. 4 Share this post Link to post Share on other sites
adsm08 3,678 #28 Posted Monday at 11:51 PM Overhead door got hung today: Goes up easier than the 6ft doors on the other side. And I got the lift post locations marked for Wednesday. 2 1 Share this post Link to post Share on other sites
adsm08 3,678 #29 Posted 9 hours ago Floor got poured today: New section of the shop is off limits to foot traffic for two days, all other traffic for two weeks. Also got a chance to talk to the lift guy, he said call him in two weeks and he'll grab two guy for a Saturday and come put it up. 1 3 Share this post Link to post Share on other sites